Definition

Penalty clause (clause pénale)

Under French law, a penalty clause is the provision by which the parties set in advance the sum payable by whichever of them fails to perform. Article 1231-5 of the French Civil Code governs it: the sum is fixed, but the court may reduce or increase it where it is manifestly excessive or derisory.

What is a penalty clause in French law?

Article 1231-5 of the Civil Code covers the contract which provides that the party failing to perform will pay a certain sum as damages. The amount is settled at signature, before any breach and without knowing what loss a breach would cause.

The clause does two things. It compensates: the creditor receives the agreed sum without having to quantify or prove its loss. It deters: the debtor knows from the outset what a breach will cost.

The sum is a fixed amount. The article states that the other party may be awarded neither more nor less. The creditor cannot claim a higher figure by proving a greater loss, and the debtor cannot pay less by proving a smaller one, subject to the court’s power described below.

A reader used to common law systems should not read “penalty” as “unenforceable”. In French law the clause is valid and applied as written, and the word has nothing to do with criminal law. Its heading matters little: “penalties”, “liquidated damages” or “fixed compensation” often describe the same thing, and the court characterises the clause by its content.

When does the penalty become due?

The penalty is incurred only once the debtor has been given formal notice to perform (mise en demeure): this is the last paragraph of Article 1231-5. Until the creditor has formally called for performance, delay alone does not trigger it.

Under Article 1344 of the Civil Code, formal notice is given by a summons or by any document that makes a sufficiently clear demand, such as a letter expressly requiring performance. The same article allows the contract to provide that the obligation falling due is in itself notice. Many commercial contracts therefore state that penalties run from the first day of delay, with no further step.

The article dispenses with notice in one case, where non-performance is final. Once confidential information has been disclosed, or a trade fair has taken place without the stand that was ordered, calling on the debtor to perform would be pointless.

The penalty otherwise follows the rule for all contractual damages: it is not due where performance was prevented by force majeure (Article 1231-1 of the Civil Code).

Can the court change the amount?

Yes, in two cases set out in Article 1231-5.

A manifestly excessive or derisory penalty. The court may reduce or increase it, even of its own motion, that is, without either party asking. The adverb matters: the article does not target a penalty that is merely high, but one whose disproportion is obvious. In practice courts assess it by comparing the agreed sum with the loss the creditor actually suffered.

Partial performance. Where the undertaking has been performed in part, the court may reduce the penalty in proportion to the benefit that partial performance gave the creditor. Here too it may act of its own motion.

A rule the contract cannot set aside. Any provision contrary to these two powers is deemed unwritten. A clause declaring the penalty “final and not open to revision” does not stop the court from reviewing it.

Revision remains discretionary. A court that does not find the penalty manifestly disproportionate applies the amount stated in the contract.

How does it differ from similar clauses?

Limitation of liability clause. It sets a maximum: the creditor must prove its loss and is compensated only up to the cap. A penalty clause sets a fixed sum, due without that proof. The power of revision in Article 1231-5 applies only to the latter; a limitation of liability clause is subject to other limits.

Withdrawal clause (clause de dédit). It gives a party the right to leave the contract on payment of a sum. The party using it commits no breach: it exercises an option the contract provides. The sum is the price of that freedom, not a sanction for non-performance. The Cour de cassation has long inferred that the court cannot reduce it as it would a penalty clause.

Periodic penalty payment (astreinte). It is ordered by a court, not agreed between the parties. Under Article L. 131-1 of the French Code of Civil Enforcement Procedures, any court may, even of its own motion, order an astreinte to secure compliance with its decision. Article L. 131-2 adds that it is independent of damages: it comes on top of them, whereas a penalty clause takes their place.

Are late payment penalties a penalty clause?

No. Between businesses, late payment penalties arise from statute: Article L. 441-10 of the French Commercial Code. They fall due on the day after the payment date shown on the invoice, and no reminder is needed.

Their rate is regulated. Payment terms may not set a rate lower than three times the French legal interest rate. Where they are silent, the rate is that of the European Central Bank’s most recent refinancing operation plus 10 percentage points.

A fixed sum for recovery costs is added, owed automatically by any business that pays late. It amounts to 40 euros (Article D. 441-5 of the Commercial Code). The creditor may claim further compensation if it shows that its costs were higher.

The Commercial Chamber of the Cour de cassation held in 2011 that these statutory penalties are not a penalty clause: the court cannot reduce them on the ground that they are excessive. A fixed percentage uplift on the unpaid debt, added by the contract, is by contrast a penalty clause subject to Article 1231-5.

Outside that regime, late payment of a sum of money gives rise to interest at the legal rate from formal notice, without the creditor having to show any loss (Article 1231-6 of the Civil Code).

Where does it appear in commercial contracts?

Late delivery or completion. The contract provides a sum per day or per week of delay, often capped at a percentage of the price. A specific text governs the penalties a retailer applies to its supplier, Article L. 441-17 of the Commercial Code: they must be proportionate to the loss suffered, may not exceed 2% of the value of the products ordered in the category concerned, and may not be deducted automatically from the invoice.

Service levels. In a hosting, maintenance or outsourcing contract, penalties sanction a missed availability rate or response time. The point to check is how they relate to the liability cap: depending on the contract, they count towards the cap or come on top of it.

Confidentiality, non-compete and non-solicitation. The loss caused by a disclosure or by poaching staff is hard to quantify. A fixed sum per breach avoids that evidential debate, which explains why it is so often found in a confidentiality clause or a non-solicitation clause. Non-performance is usually final in these cases, so the penalty is due without formal notice.

Consumers and leases: what are the specific rules?

Consumer contracts. Article R. 212-2 of the French Consumer Code presumes unfair a term requiring a defaulting consumer to pay compensation of a manifestly disproportionate amount. The presumption is rebuttable: the business may prove otherwise. A term found unfair is deemed unwritten. It therefore falls away entirely, whereas Article 1231-5 only leads to its amount being revised.

Residential leases. Article 4 of the Act of 6 July 1989 deems unwritten any term allowing the landlord to collect fines or penalties for a breach of the lease or of the building’s rules. In a lease governed by that Act, a penalty clause against the tenant therefore has no effect.

Commercial leases. There is no comparable prohibition. An uplift on unpaid rent, or a fixed occupation charge due after the lease ends, may be characterised as a penalty clause, which the court may then revise.

In practice

  • A machine manufacturer accepts penalties of 0.5% of the price per week of delay, capped at 5%: it knows at signature the maximum cost of late commissioning.
  • A software vendor checks whether the availability penalties in its service level agreement count towards the contract’s liability cap or come on top of it.
  • A legal department receiving a customer’s purchasing terms spots the clause that makes penalties run without formal notice and the one that declares them not open to revision, the latter having no effect before a court.
  • On an unpaid invoice, an accounts team separates the statutory late payment penalties and the 40-euro recovery sum from the fixed uplift provided in the contract, which alone is open to revision by the court.

In Docform

Docform’s clause library centralises the clauses approved by legal, with their variants and variables, and links them to contract templates. The playbook turns your contract policy into review rules, with a severity and a preferred position: the assistant flags deviations in the contract received and quotes the passage concerned. The decision stays with your team.

Frequently asked questions

What is a penalty clause under French law?
It is the clause that sets in advance the sum owed by the party that fails to perform. It is governed by Article 1231-5 of the Civil Code. The sum is fixed: the creditor receives it without having to prove the amount of its loss.
Can a French court reduce a penalty clause?
Yes. It may, even of its own motion, reduce a manifestly excessive penalty or increase a manifestly derisory one. It may also reduce it where the contract was partly performed. Any provision to the contrary is deemed unwritten.
Is formal notice required before claiming the penalty?
In principle yes: the penalty is incurred only once the debtor has been given formal notice. The article lifts that requirement where non-performance is final, and Article 1344 of the Civil Code allows the contract to provide that the obligation falling due is in itself notice.
How does a penalty clause differ from a limitation of liability clause?
A penalty clause sets a fixed sum, due without proof of loss and open to revision by the court. A limitation clause sets a cap: the creditor must prove its loss and is compensated only up to that limit.
Are late payment penalties a penalty clause?
No. Between businesses they are provided for by Article L. 441-10 of the Commercial Code, with a minimum rate of three times the legal interest rate and a fixed recovery sum of 40 euros. The Cour de cassation held in 2011 that the court cannot reduce them as it would a penalty clause.
Is a penalty clause valid against a consumer or in a residential lease?
Against a consumer, compensation of a manifestly disproportionate amount is presumed unfair (Article R. 212-2 of the Consumer Code). In a residential lease governed by the Act of 6 July 1989, a term allowing the landlord to collect penalties is deemed unwritten.

Disclaimer

This page provides general information on French law. It does not constitute legal advice and does not replace your counsel’s review of a specific contract.